Key Facts

  • Client
    Girls Day School Trust
  • Value
    £169,000
  • Form of Contract
    Form of contract: Minor Works with contractors design portion
  • Project Duration
    6 weeks

Bromley School – Girls Day School Trust

Diamond Build plc successfully completed their first project with the Girls Day School Trust on time.

The project at Bromley School entail the modernisation of changing rooms and toilets over the summer recess. As a consequence it was imperative the Facilities were available for the return of the pupil.

Key to our success was the use of prefabricated and in particular the design management of these goods

The facilities manager made mention that Diamond Build were the must considerate and tidy contractor he had worked with at the school.



News

DIAMOND BUILD GROUP COMMITS TO ‘EARN AND LEARN’ INITIATIVE

Diamond Build Group has joined The 5% Club, an industry-led initiative focussed on...

More >>

Project Spotlight: Transforming Office Space in Old Street, London

Client: London Borough of Islington Architect: Islington Architects Value: £3.5m Duration: 34 weeks...

More >>

In Conversation With: John Gray

John Gray spent nine years training with a national contractor and honed his...

More >>

DIAMOND BUILD GROUP ACHIEVES INVESTORS IN PEOPLE GOLD ACCREDITATION

Diamond Build Group has achieved the prestigious Investors in People gold accreditation. The...

More >>